During Program Increment (PI) planning, which statement is true about the activities of team breakouts?

  1. At team breakout #1 (day 1), teams finalize their projects

  2. At team breakout #2 (day 2), teams work to create their final plans

  3. Team breakouts are not necessary

  4. Team breakouts occur only after the PI planning

The correct answer is: At team breakout #2 (day 2), teams work to create their final plans

During Program Increment (PI) planning, the activities of team breakouts are designed to enable teams to plan their work in detail. Specifically, in the second team breakout on day two, teams focus on refining and finalizing their plans for the upcoming Program Increment. This includes identifying specific stories, tasks, and objectives they will commit to delivering, as well as assessing any dependencies and risks associated with their plans. The emphasis on creating final plans during this breakout is critical, as it allows teams to align their efforts with the overarching program goals and ensures that they are prepared to execute the work in the coming days. This collaborative environment fosters communication and teamwork, ensuring that all team members have a clear understanding of the objectives and responsibilities. The other options do not accurately reflect the purpose and activities associated with team breakouts during PI planning, further validating that the second breakout is indeed when teams refine their plans.